Open Access Metro (OAM), a division of WIOCC, designs, builds, and maintains a high-performance wholesale fibre network that enables ISP partners to serve homes and businesses. Its current network spans more than 3,000 kilometres, passes more than 3 million premises in Lagos, and connects more than 500 estates.
With continued investment and rapid growth across Lagos—and plans to extend its footprint into new regions over time—OAM must evaluate proposed builds efficiently. Previously, evaluating a typical 2,000-unit estate required planners to manually validate the design, calculate materials and costs, and prepare the business case—a process that took approximately four days.
The Solution
A repeatable path from contractor design to construction
Open Access Metro now uses VETRO to review proposed designs, auto-generate the information needed to make investment decisions, and carry approved designs directly into construction.
-
Structured Design Intake: Contractors submit designs using Open Access Metro templates, allowing the proposed network to be imported into VETRO for review.
-
Faster Design Validation: Planners inspect feature quantities and validate the proposed layout without manually counting every service point and route.
-
Generated BOM and PET: VETRO generates the Bill of Materials (BOM) and Price Estimate Template (PET). The PET output is then incorporated into Open Access Metro’s business-case template for a go-or-no-go decision.
-
From Approval to Construction: Once the business case is approved, the same design used to generate the BOM and cost estimate is issued to the contractor with the required construction files and labels. Contractors can begin work using the design that Open Access Metro has already reviewed, approved, and costed.
The Result
Four days compressed into one morning
-
A Complete Business Case in About Three Hours: When a contractor’s design meets Open Access Metro’s requirements, planners review the design and complete the BOM, PET, and business case in one morning.
-
Less Manual Work: Automated quantities and cost outputs replace service-point counting, manual BOM development, and preparation of a separate bill of services.
-
Greater Budget Certainty: Basing the BOM, PET, and investment decision on the same reviewed design gives Open Access Metro a consistent set of quantities and projected costs, helping the team assess whether a proposed build is likely to remain within its approved budget.
-
Faster Construction Starts: Once an investment is approved, Open Access Metro can issue the same approved and costed design directly to the contractor so work can begin without recreating or translating the plan.
“VETRO enables us to move quickly and confidently. The design we approve is the design we cost and the design the contractor builds. That gives us tighter control of the investment and keeps everyone aligned from the business case through construction.”
Open Access Metro
About VETRO
At VETRO, our vision is to empower network operators to master escalating complexities and lead the charge in defining the future of global connectivity. Our Network Infrastructure Management and Orchestration Platform is the cornerstone for building future-ready infrastructure, transforming the entire lifecycle of physical network assets.
By establishing a cohesive system of record and enabling intelligent, automated workflows, we empower our clients to move beyond legacy systems, unlock efficiencies, deploy advanced technologies, and connect more communities to the digital world faster than ever before.